RERA registration: a developer's pre-launch checklist

Thresholds, documents and the separate-account rule — before the first advertisement.

Under the Real Estate (Regulation and Development) Act, 2016, a project that must be registered cannot be advertised, marketed or sold until it is. A delayed registration delays the entire launch.

Does the project need registration?

Projects on land exceeding 500 square metres, or with more than eight apartments, must be registered — and some States set lower thresholds. Phased projects need careful treatment.

Documents that slow things down

Title documents, sanctioned plans, encumbrance details and the development agreement with landowners are the usual bottlenecks. Collecting them early prevents a gap between approval and launch.

The 70% account

Seventy per cent of amounts realised from allottees must be held in a separate account and used only for construction and land costs of that project. Systems to track this should be in place before collections begin.